Uganda pushes first oil output to mid-2027

Uganda's national oil company and petroleum authority now expect the country's first oil production and exports before the end of June 2027. Officials blame the delay on international supply-chain bottlenecks and disruption linked to the war in Iran. Finance Minister Henry Musasizi said the slip is expected to open a significant budget gap, since the 2026/2027 budget projected petroleum revenues of 1.44 trillion Ugandan shillings (about $380 million). The $5.6 billion East African Crude Oil Pipeline, which runs 1,443 km to Tanga Port in Tanzania, is more than 90 % complete, though pump stations three and four and several control and security systems are unfinished.

Key facts

  • The 1,443-km pipeline links western Uganda to Tanga Port in Tanzania.
  • Thermal integration is required before oil can flow because Ugandan crude is waxy.
  • Central Processing Facilities that treat and stabilize raw crude are still being installed and pre-commissioned.

Summarised with AI from 1 sourceRead our AI policy

Why it matters

The delay pushes back Uganda's expected oil revenue and widens a projected budget shortfall.